Progress photos and update 6/12/22
We are in the final stages of the disabled access toilet installation; it is programmed for completion by the end of the week. The new door has been installed and the original infilled to provide an area for shelving on the inside of the toilet and a notice board on the outside. All the drainage connections are installed with the EPPH returning on Thursday to complete the installation of the toilet and basin. The partition between the main hall and toilet has been adjusted to allow for easy access through to the toilet, people will no longer have to bend to get through. ESP have been busy installing additional sockets including a 32Amp for the coffee machine and other electrics associated with the disabled access toilet.