Progress photos and update 6/12/22

We are in the final stages of the disabled access toilet installation; it is programmed for completion by the end of the week. The new door has been installed and the original infilled to provide an area for shelving on the inside of the toilet and a notice board on the outside. All the drainage connections are installed with the EPPH returning on Thursday to complete the installation of the toilet and basin. The partition between the main hall and toilet has been adjusted to allow for easy access through to the toilet, people will no longer have to bend to get through. ESP have been busy installing additional sockets including a 32Amp for the coffee machine and other electrics associated with the disabled access toilet.

 

Photograph shows completed waste installation

 

Photo shows completed door installation ready for decoration by volunteers!

 

Original door infilled and ready for shelves to be installed by volunteers. View from inside the toilet.

 

Original door infilled and ready for decoration by volunteers, View from bar area

 

New sinks and water heater installed in the bar storage area including connections for glass washer. Additional sockets provided.

 

David (Gipping Construction), Jason and Ray from ESP in front of the new sinks

 

Partition wall removed to provide walkway through to the toilet.

 

Simon, Sheila (JPC Directors), David (Gipping Construction), Ray (ESP) and Eden (Gipping Construction) standing where the disabled access toilet will be located by the end of the week!