Completed Gipping Works
Photos by Paulin Goonan – Taken on 22/12/22
Read moreThe toilet is in but now we need water!
Lots of new sockets installed by ESP 32Amp power connection for coffee machine installed, waste pipe being installed today by
Read moreProgress photos and update 6/12/22
We are in the final stages of the disabled access toilet installation; it is programmed for completion by the end
Read moreProgress to Monday 28/11/22.
The plumbers from epph were in today working on the drainage connections. (The men in the photo are Todd and
Read moreJon Parker
The John Peel Centre feel very lucky to have so many people helping us out to get this initial phase
Read moreBuilding Control Visit
We had our first visit from Matt from Mid Suffolk Building Control yesterday, we discussed and agreed the route for
Read morePop Up Bar Phase
It was always the dream of the John Peel Centre team to expand into 11 Market Place (the former National
Read moreSigning the lease
After a long period of negotiation, we are excited to report that we have signed the lease to take over
Read moreScott Matthews 23.09.22